Phase Activity Start Date End Date Duration (Days)
Inception New Project Committee or Fast-Track Proposal 2026-03-31
30
Planning Plan Tasks 2026-04-01 2026-04-30
30
Planning Governing Committee Review (14-day minimum) 2026-05-01 2026-05-14
14
Planning Governing Committee Approval (14-day minimum) 2026-05-15 2026-05-28
14
Development Development Tasks 2026-05-29 2026-07-27
60
Development Project Committee Approval (not required for Fast-Track) 2026-07-28 2026-08-10
14
Development Governing Committee Approval (14-day minimum) 2026-08-11 2026-08-24
14
Stabilization Internal Review (14-day minimum) 2026-08-25 2026-09-07
14
Stabilization Stabilization Tasks 2026-09-08 2026-10-07
30
Stabilization Project Committee Approval (not required for Fast-Track) 2026-10-08 2026-10-21
14
Freezing ARC Freeze Approval 2026-10-22 2026-12-05
45
Freezing RISC-V Compliance 2026-12-06 2026-12-12
7
Freezing Freeze Tasks 2026-12-13 2026-12-27
15
Freezing Governing Committee Approval (14-day minimum) 2026-12-28 2027-01-10
14
Ratification-Ready Public Review (30-day minimum) 2027-01-11 2027-02-09
30
Ratification-Ready Ratification-Ready Tasks 2027-02-10 2027-02-24
15
Ratification-Ready ARC Ratification Approval (if substantial changes after public review) 2027-02-25 2027-02-25
0
Ratification-Ready TSC Approval (14-day minimum) 2027-02-25 2027-03-10
14
Publication BoD Approval 2027-03-11 2027-03-25
1